Meissner Filtration Products

Castlebar, Co. Mayo.

A two storey building, Approx 3000 containing a cleanroom production area, office space and warehouse.

Project completed in 2020. 

Scope of Works Included:

  • MV Switchgear & MV Cabling Installation.

  • Transformer Installation.

  • Main Distribution Board Installation.

  • Sub-Main Distribution Board Installation.

  • Power Factor Correction Installation.

  • Energy Monitoring Data Logger Installation.

  • Sub-Mains Cabling Installation.

  • Electrical Containment Installation.

  • Lighting and Emergency Lighting Installation..

  • Lighting Controls Installation.

  • Fire Alarm and Air Sampling System Installation.

  • General Services Installation.

  • Voice/ Data Installation.

  • Access Control installation.

  • CCTV System (Wiring Only).

  • Public Address (Wiring Only)

  • Wiring Associated With Mechanical Services Installation.

  • Earthing / Testing / Commissioning.

  • Record Documentation & As-Built Drawings.